Sunday, May 5, 2013

Pay Now, Argue Later and CIPAA 2012

The Kuala Lumpur Regional Centre of Arbitration (KLRCA), has often summarised the core concept of the Construction Industry Payment & Adjudication Act 2012 (CIPAA 2012) to be "Pay Now, Argue Later". CIPAA 2012 was introduced in Malaysia with the sole aim of addressing the payment problem faced by sub-contractors, suppliers, agents, professional service providers, (collectively referred to "Claimant") etc in the construction industry, whose only remedy for payment disputes was costly and protracted litigation in either the court or arbitration. Now, payment disputes can be brought before KLRCA certified adjudicators for speedy and cost effective decision.

What happens when the Claimant/ himself does not come to the adjudicator with "clean hands"? What happens if the Claimant has been accused of defective work which has resulted in non-payment by the Respondent? Pay Now, Argue Later will have a bearing on the payment dispute as the adjudicator will be tasked in determining the extent of work done and decide the amount to be paid.


Defective Work In Construction Projects

The nature of defective work

The nature and type of defects in construction and engineering projects can vary, and not forgetting that the point at which the defects become apparent. On one end of the scale minor defects can easily be corrected before the building or plant is handed over to the employer, while at the other extreme major or significant defects may occur long after the original work has been completed and require extensive remedial works to fix.

Some of the defects can arise because the work was not carried out in a 'good and workmanlike manner' in accordance with good practice or a particular design, or because the wrong materials have been used – matters which would usually be the responsibility of the building contractor and its supply chain. 

Alternatively a particular design is not working in the manner that it should as the designer could be at fault

In the frequently used design and build scenario, the contractor would normally have primary liability for both types of failure – although it may have consequential claims against its designers and supply chain.

On one view identifying a defect should be easy: something has usually not been provided in the manner that it should have been, the foundations of a building could crack and subside, the air-conditioning units fail or the roof leak. However, in considering 'defects' as a matter of principle, work may be defective even if it has been carried out with all due skill and care but it fails to meet a particular specification. 

For example, brickwork may be erected correctly but the wrong type or colour of brick could have been used in breach of planning permission.

Potentially difficult arguments can arise where work has been carried out incorrectly by the contractor but the architect or engineer's design is also at fault. In these situations, the contractor may deny liability on the basis that even though the work was carried out defectively, it did not cause the damage complained of. An employer will not be as concerned as the contractor and architect to get to the bottom of exactly who is at fault for that as long as it can claim against one or both of the parties and both still exist.

It is often important to distinguish between patent and latent defects. A patent defect is one that is detectable either at or before apparent practical completion or during the defects liability period. In the past, the courts have held that patent defects must be apparent on inspection but need not necessarily have been seen by the people carrying out that inspection. By contract, a latent defect is one which has been concealed in the works and may not become apparent for many years.

Typical contractual provisions
The standard form construction contracts contain provisions dealing with the treatment of defective work during the course of construction, at completion and during the defects liability or rectification period. By way of illustration, the contract form may provide that the employer may issue instructions requiring the opening up for inspection of any work covered up or tests of materials or goods or executed work. The cost of opening up or testing is added to the contract sum, unless the inspection shows that the materials, goods, or work are not in accordance with the contract - the contractor then bears those costs.

The question of defects often arises in the context of practical completion (PC), and whether or not completion can be said to have occurred even though minor defects exist. In the absence of any definition, guidelines have been developed from case law which broadly state that:
  • ·         at the date of practical completion the work should be complete and free from patent defects;
  • ·         PC will be achieved notwithstanding the presence of latent defects, because such defects are by definition not apparent;
  • ·         any defects which are not apparent at PC which do become evident during the defects liability period may be addressed in that period;
  • ·         discretion usually exists to certify PC when minor work remains to be carried out, although it is possible to insist on completion of all snagging items before PC.


Rights and remedies
An issue which often arises in the context of construction projects is whether the contractor has a 'right to return' to the site to remedy defects. However, there is no such right unless one is specifically conferred upon the contractor by the defects liability provisions or otherwise in the contract. Where there is no express right for the contractor to return to the site to attend to remedial works, or the relevant period has passed, an employer is entitled to employ others to rectify defects. However, where a third party is appointed and that is thought to be unreasonable in the circumstances of the case then the employer may be criticised for failing to mitigate its loss.

The standard forms use different terminology for the defects rectification period, including 'rectification period', 'maintenance period' and 'defects correction period'. The nature and scope of such periods depend on the mechanism adopted in the particular contract, and they are typically seen as applying to the whole of the works, the relevant part or section. The length of the period will be negotiated by the parties and the nature of the works to be undertaken.

In circumstances where defective work is present, several legal remedies may exist. Starting with remedies in contract, where defective work is present as a consequence of a breach of contract then a claiming party is entitled to be put into the position it would have been if the work had been correctly carried out. This is achieved by a monetary award. The claiming party's losses may be assessed on the basis of:
  • ·         the reasonable cost of repair of the defect work;
  • ·         the difference in value or loss of amenity of the relevant work.

In strict legal terms the date for assessment of the loss is when the defect is noticed, but when considering the cost of repair the date of assessment is usually taken as when it is reasonable in the circumstances to undertake the relevant works. A party seeking to bring an action for breach of contract in relation to defective works has six years to do so if the contract is executed under hand (signed by a single, authorised representative) or 12 years if the contract is executed by deed. Those periods run from the date of the breach of contract. In the case of patent defects this should be obvious, as it is the date when the defective work is carried out, but for latent defects the date of cause in action is usually taken as being the date on which PC is certified or given. Similar considerations would arise in relation to allegations of defective design. 

Betterment
Where repair works result in a better or newer building, a deduction in damages will not usually be made if the claiming party had no reasonable choice but to undertake the works in that way. However, if a party chooses to rebuild to a higher standard than was strictly necessary it may only be entitled to recover the cost of those works less a credit for the betterment element of it. While each case will turn on its own facts, if works are said to be unnecessarily expensive the test to be applied is whether the claiming party acted reasonably in proceeding in that way. If not, it may struggle to recover the additional costs.

Pure Economic Loss
Defects in buildings can also pose significant problems for subsequent owners who take on responsibility for a building without having procured the relevant work. This is because there would be no claim in contract, unless separate rights or a warranty had been conferred on that new owner. If this situation arises and the subsequent owner has no remedy in contract it raises the question over whether the owner can recover its costs and losses in any other way, for example in tort. The general rule is that damage to a building which is attributable to a defect in the structure of that building is not recoverable – such damage is known as 'pure economic loss' as the only loss sustained is the fact that the new owner has paid too much for the property. 

In 2011 the Court of Appeal clarified that, ordinarily, contractors will not owe duties not to cause pure economic loss. Therefore they will not owe such duties to subsequent owners.

Limited exceptions may apply if the new owner is able to show that the contractor had assumed responsibility for that loss through the provision of skilled advice or services or at least some design responsibility, and that the owner had relied on that advice or services or design. Such situations have been held to arise, for example, where a specialist subcontractor provides services to the contractor who employed it and where a civil engineer provided design services. However, such situations are complicated and the preferable route would always be to ensure that any new owner had the appropriate contractual protection to try and guard against its losses.

Set off, abatement and withholding
Defective work also raises issues relating to certain 'self help' remedies, including common law set off or abatement and equitable set off.

Common law set off or abatement: A summary of the legal principles :-

  • ·         in a contract for labour and materials where performance has been defective the employer is entitled to maintain a defence of abatement;
  • ·         the measure of the abatement is the amount by which the product of the contractor's endeavours has been diminished in value as a result of the defective performance;
  • ·         depending on the facts, this difference may be determined by comparing the market value of what has been constructed with what ought to have been built, or by reference to the cost of remedial works (but not the cost of the remedial works themselves);
  • ·         the measure of abatement can never exceed the sum which would otherwise be due to the contractor as payment;
  • ·         abatement is not available as a defence to a claim in respect of professional services;
  • ·         claims for delay, disruption or damage caused to anything other than that which the contractor has constructed cannot feature in a defence of abatement.

Equitable set-off
This is permitted where a party has a cross-claim which it would be unjust not to take into account. This is a wide test and will cover any cross-claim 'closely connected' with the claim being made.

The issues surrounding set off and abatement lead us to the restrictions on those rights under CIPAA 2012. The Act provides that a party to a construction contract may not withhold payment after the final due date. Period. Unlike similar statute in the UK which provides that a party may not withhold payment after it becomes due unless it gives an effective notice of its intention to withhold payment including its grounds for doing so to the other party. This is to stop contractors abusing their position to wrongfully withhold sums due to subcontractors who typically have no quick or cheap means to challenge the withholding. 

The "Pay Now, Argue Later" principle of CIPAA 2012 may result in prolonged litigation. The losing party of the adjudication decision will seek to appeal the decision in court and stay the execution of the decision. This will certainly defeat the noble aim of CIPAA 2012 to resolve payment disputes quickly and cost effectively.

Practical issues
As a starting point, it is worth thinking about how defects and completion issues should be addressed at procurement stage. Whether something is defective will often depend not so much on whether it is completed competently from a workmanship perspective but on the precise standard and specification to be met. Similarly, if specific tests are to be passed these will need to be provided for contractually, and consideration given to whether general or liquidated damages should apply in the event of failure. The precise standard and level of completion required for PC is something which can often cause arguments, so careful consideration should be given to whether the completion requirements are clear and what risks they may hold.

It goes without saying that those passing their obligations down a supply chain should seek the same assumption of responsibility in relation to defects.

Turning to the execution phase of the contract, the practical issues tend to focus around evidence and notices. Defects are most likely to be picked up on site if there is regular monitoring and testing. It will be a commercial judgement for employers and contractors as to how much they wish to spend monitoring and testing the works, but what is crucially important is that if defects are identified that are likely to have implications for the project then comprehensive records will need to be taken. Similarly, if it is intended to reduce a payment or advance a claim as a result of a defect, then consideration should very rapidly be given to the basis of the claim. It is also not uncommon for issues to arise as to whether an employer waived or agreed to allow a defect to remain. Again, evidence of agreement or waiver should be obtained.
Post completion, if a defect occurs within a defects liability period under a contract then in all probability the employer will be entitled to require the contractor to correct the defect. In some forms this is the case even if it is not clear that the defect is the contractor's responsibility, although the contractor will be entitled to payment if it is proved the defect is not one for which is it responsible.

Clearly, early consideration should be given to the contractual procedures and relevant notices. Even if the defects liability period has ended the contractor will in the vast majority of cases remain liable in damages.

If you are an end user who did not employ the contractor or design team then you will want to consider whether you have the benefit of any assignment of the relevant building contract or professional appointments, or alternatively whether you have collateral warranties or third party rights.

YONG MOK HIN v. UNITED MALAY STATES SUGAR INDUSTRIES LTD
[1964] 1 LNS 230
DW3, a civil and structural engineer, who inspected the work at the end of the same year also testified about the defective work as enumerated in para. 7 of the statement of defence. The plaintiff sought to argue that the architect had supervised the work and had issued the certificate Exh. P2, had signed in the plaintiff's pass book, and lastly the defendant company had by their letter stated that the work was satisfactory. In my judgment such certificate or letter only represents the approximate value of the work done or materials used. It is not conclusive on the parties as an expression of satisfaction with the quality of the work or materials. That is subject to readjustment upon the issue of the final certificate. Having considered the evidence, I am satisfied that the work was defective and was due to bad workmanship.

The defendant company opted to accept repudiation and sue for damages for incomplete and defective work. The law with regard to the measure of damages is adequately stated at p. 442 of the 9th Edn. of Hudson on "Building and Engineering Contracts".
... the direct measure of damage will be the difference between the reasonable cost to the employer of repairing the defects or completing the work, together with any sums paid by or due from him under the contract, and the sums which would have been payable by him under the contract if it had been properly carried out. (Where the former does not exceed the latter, only nominal damages would be recoverable). Such damages are clearly recoverable within the first branch of the in Hadley v. Baxendale [1854] 9 Ex 341 as likely to arise in the usual course of things from the breach".
The editor cited several authorities and I think it would be sufficient if I only cite the case of Hirt v. Hahn [1876] 61 Missouri 496.
B agreed to erect a house for the plaintiff according to plans by a certain day. The defendants were B's sureties. After partly completing, B ceased work, and the plaintiff, after giving notice to the sureties, entered and completed and sued the sureties. Held, that the measure of damage was what it cost the plaintiff to complete the house substantially as it was originally intended, and in a reasonable manner, less any amount that would have been due and payable to B by the plaintiff had B completed the house at the time agreed by the terms of his contract".

That is an American case but the principle enunciated was approved by the Court of Appeal in Mertens v. Home Freeholds Co [1921] 2 KB 526 at p. 535 where Lord Sterndale said:
It is true that that is an American case. Though I cannot put my finger on them for the moment I feel satisfied that there are English cases which fix the same measure of damages. At any rate for the purpose of this case it is sufficient to say we all consider that the proper measures of damages for the breach of a building contract such as this".

However, the cost of completion means the cost of completing the contract work, but not different work. Thus in Milwaukee City v. Shailer [1898] 84 Fed Rep 106 another American case, Shailer contracted to construct a tunnel for the city. The contract provided that in case of default, the city should be entitled to complete the work at Shailer's expense. On Shailer's default the city constructed a tunnel which was essentially different in plan and cost of construction from that contemplated by the contract. It was held that the city was not entitled to recover damages from Shailer.

Mr McDonald, a quantity surveyor, testified that a total sum of $377,221.92 would be the cost of remedying defective work and completing the project from where the plaintiff had left it. He based his valuation on the current and appropriate building rates for this quality of work pertaining to this part of Malaysia. It must be borne in mind that the original contract price was $187,500, and the figure quoted by DW6 would therefore include the cost for the variation and remedying defective work. The cost of putting right defective work, he stated, was $21,095.75. Therefore, arithmetically, $168,720 would be the cost of the extra work. In this connection the cost of extra work must be considered in the light of all the surrounding circumstances. Thus an employer may have deliberately chosen a small-time contractor with limited resources of capital, plant and labour to do the work in the hope of getting a cheaper job. The plaintiff is a class 'E' PWD contractor with a ceiling of $50,000. As no fixed amount was agreed upon in respect of extra work, and considering that work was to be done by a contractor of the same class as the plaintiff, and in view of the principle enunciated in Milwaukee City v. Shailer, supra, I would consider a sum of $126,540 (750f $168,720) as reasonable. In the circumstances, the amount that would cost the defendant company to complete the work and remedy defects would be $335,135.75.

As against that amount must be deducted the contract price as varied that would represent the costs which the plaintiff would have expended on the whole project as varied. I assess that figure in the following manner:
Original contract price $187,500
Extra work 74,000
;$261,500.00 ($74,000 is made up of $24,000, the cost of alteration from zinc walls to 9" brick walls; $40,000 for a third store; and $10,000 for labour and miscellaneous expenses). From the amount of $261,500 must be deducted the sum of $36,000 as representing the fifth progress payment. Therefore the amount which would be due to the plaintiff would be $225,500.

The measure of damages would be the difference between the reasonable costs of completing the work as varied and the amount that would have been due to the plaintiff had he completed the work as varied, and that is $109,635.75.


No comments:

Post a Comment